Lane and shoulder closures begin March 17 on I-65 in Scott, Clark Counties

SCOTT/CLARK CO. – Indiana Department of Transportation contractor HydraTech Field Services plans to begin repair work next week on two bridges over I-65 in Scott and Clark Counties. Work will take place simultaneously at both locations listed below. Joint replacement and barrier wall repair are also planned later this spring at the third location on S.R. 3 in Scott County.

S.R. 56 over I-65 – Scott County
Starting on or after Wednesday, March 17, crews will begin repair work on the center pier of S.R. 56 over I-65. This will require inside shoulder closures for both directions of I-65.

Overnight lane closures are expected to begin at the overpass in early May, starting with the right northbound lane. The right southbound lane and entrance ramp from S.R. 56 will close nightly starting in mid-May. Each lane will close at approximately 9 p.m. each night and reopen each morning around 6 a.m.

Ebenezer Church Road over I-65 – Clark County
Also starting on or after March 17, work will begin on the center pier of Ebenezer Church Road over I-65. Crews will start on the northbound side of the pier and move to the southbound side in mid-April. Single-lane closures will be required in one direction at a time for the duration of the project.

S.R. 3 over Abandoned Railroad – Scott County
Bridge joint replacement and barrier wall repair is scheduled to begin in mid-May on S.R. 3 over an abandoned railroad in Scott County. The bridge is located south of Blocher, approximately half a mile south of the north junction of S.R. 3 and S.R. 56. Work will be completed during the day under lane closures with flagging.