Curb Ramp, Asphalt Resurface Work Begins on State Road 256 in Austin Monday

(SCOTT CO.) – A $586,000 curb ramp replacement and asphalt resurfacing project is scheduled to begin on or after Monday, July 15, 2019 on State Road 256 in Austin. Work will take place from Dowling Street, near I-65, to US 31.

INDOT contractor MAC Construction will begin with curb ramp removal and replacement, followed by center curb removal, milling, and asphalt paving.

Lane restrictions will be in effect along the route, mainly while milling and paving work is in progress. Please use caution in and around the work zone.

The project is expected to be complete by September 30, 2019.

All work is weather dependent.