Crews Will Mill And Pave Lincoln Avenue And J Street Beginning Monday

(BEDFORD) – Crews will be milling and paving Lincoln Avenue and J Street next week.

Milling will be done on Lincoln Avenue from the roundabout north to Sixth Street on Monday, August 24th. Crews will begin paving that area on Tuesday, August 25.

Milling will then be done on J Street from Fifth Street to 14th Street on Tuesday, August 25th.

All businesses will remain open.

City officials ask that motorists drive carefully and avoid this route if possible. Use alternate side routes as necessary. 

The schedule is dependent on weather conditions.