(COLUMBUS) - Work has been completed on an overhaul of a runway at a southern Indiana airport that officials expect will boost traffic.

The $5 million project at the Columbus Municipal Airport included removing 9 inches of a runway's asphalt surface and replacing it with 10 inches of concrete.

Airport Director Brian Payne tells The Republic that poor drainage along the runway led to water accumulating in the asphalt. That caused the surface to deteriorate and become a safety hazard. The drainage has been improved and the new runway is fully grooved so that planes are better able to take off and land during bad weather.

The project took three months to complete. The concrete runway is expected to last at least 30 years.



« Previous Article
Next Article »

 Print    Archive    RSS

Have a question or comment about a news story? Send it to comments@wbiw.com

Advertise with 1340 AM WBIW
Find more about Weather in Bedford, IN
Advertise with 1340 AM WBIW


1340 AM WBIW, Bedford's Place To Talk. Serving Lawrence and surrounding counties since 1948!

© 2017 Ad-Venture Media, Inc. All Rights Reserved.   WBIW.com and Listen Live Powered by HPC

Advertise  |  Careers  |  Contests  |  About  |  Feedback