Last updated on Tuesday, September 19, 2006
(BEDFORD) - Bedford Urban Enterprise Association Executive Director Jamie Harris, along with a representative from JKI Engineering, was at the Bedford Board of Works and Safety meeting explaining the change order for the Milwaukee Depot restoration project.
It was discovered the deterioration of the building was more extensive than originally anticipated.
An additional $21,000 and 17 more working days was added to finish the first phase of the construction.
Harris said it should take about another month to complete the roof replacement.