(BLOOMINGTON) - Weather permitting, some crews will be out in the I-69 Section 5 work zone this weekend, hanging signs, installing guardrail and knocking out punch list items. Most of the work is offline and won’t impact traffic.

On Monday morning, some barrels will return and punch list activity will pick up. Most construction activity will require shoulder closures and flagging operations, but motorists should be aware of some limited lane restrictions:

All construction work is weather dependent and the schedule is subject to change.