SR 46 Milling/Paving for Columbus and Nashville

Last updated on Friday, July 20, 2018

(BARTHOLOMEW & BROWN COUNTIES) — Indiana Department of Transportation’s contractor for its $4.3 million resurfacing project on the 15-mile section of State Road 46 between Columbus and Nashville will have crews operational at three different locations by the end of next week.

Currently, Milestone workers are replacing a 1200-foot full-depth section of pavement at Tipton Lakes Boulevard west of Columbus--while a second crew is milling surface asphalt in S.R. 46's westbound lane. The milling operation began July 18 at C.R. 350W in Bartholomew County.

Next Thursday, July 26, paving crews are scheduled to start placing the asphalt surface on S.R. 46's westbound lane--lagging several days behind milling operations.

Just short of S.R. 135 at Nashville, S.R. 46 milling and paving operations will turn to the eastbound lane.

Motorists will be direct around moving worksites by flaggers.

S.R. 46's traffic count between I-65 and S.R. 135 is 9,070 vehicles per day.

Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone. For highway information, monitor social media sites: www.Facebook.com/INDOTSoutheast and Twitter @INDOTSoutheast. Subscribe to receive text and email alerts at https://public.govdelivery.com/accounts/INDOT/subscriber/new.

1340 AM WBIW welcomes comments and suggestions by calling 812.277.1340 during normal business hours or by email at comments@wbiw.com

© Ad-Venture Media, Inc. All Rights Reserved.

Click here to go back to previous page