(BLOOMINGTON) - Beginning this week crews will prepare the northern segment of the I-69 construction zone for closures and restrictions that will begin as early as Monday, February 26 and remain in place until July. All work is dependent on both the weather and availability of asphalt paving material.

Crews will be removing existing paint on southbound State Road 37 from Big Indian Creek to approximately Bryant's Creek. New striping will be placed on the southbound lanes in this stretch to accommodate one lane of southbound traffic, one lane of northbound traffic and a center left turn lane for exiting State Road 37 at designated points. The asphalt crossover at Bryant's Creek will be improved to facilitate a northbound traffic shift there.

Once the preparations are completed, traffic will be reconfigured to allow for bridge demolition and shoulder reconstruction on northbound State Road 37 from Fox Hollow Road to Big Indian Creek.

The northbound lanes of State Road 37 will be reduced to a single lane at Fox Hollow Road and will cross over to the current southbound lanes at Bryant's Creek. The southbound lanes of State Road 37 will be reduced to a single lane just north of the Liberty Creek interchange and remain in single lane configuration to just south of Chambers Pike

Between Bryant's Creek and Big Indian Creek, a distance of approximately 4.8 miles, north and southbound traffic will use the existing southbound lanes with a center left turn lane. There will be no tubes or barrels separating the travel lanes, and motorists are urged to pay attention to the yellow-line pavement markings. Left turn lanes to exit mainline State Road 37 will be indicated by signage and roadway markings.

In this configuration, there will a number of access points at which motorists can enter and exit State Road 37 between Big Indian Creek and Bryant's Creek:

As construction and paving on local access roads progresses, some of these access points may close as road connectivity is completed. Public notice will be given prior to any access road closure.

Motorists are urged to pay attention to changing traffic conditions through the weekend. The final traffic configuration is anticipated to be in place late Sunday night or early Monday morning. The posted speed limit remains 45 miles per hour throughout the entire I-69 Section 5 construction zone, and drivers are encouraged to pay attention to traffic conditions, put down phones and other devices, and leave plenty of room between vehicles.

1340 AM WBIW welcomes comments and suggestions by calling 812.277.1340 during normal business hours or by email at comments@wbiw.com