I-69 One Year Behind Schedule
Updated December 27, 2016 9:12 AM
 Print    Archive    RSS

(BLOOMINGTON) - A 21-mile section of the Interstate 69 project is nearly a year behind schedule.

The Bloomington Herald-Times reports there was supposed to be a stoplight-free drive from Bloomington to Martinsville by now.

Instead, contract disputes and permit issues mean there'll be a construction zone until next summer.

The company hired to design and build the section is called Isolux Corsan USA. Company officials say the delay is due to bad soil tests and permitting, blaming the Indiana Finance Authority for not getting the right federal permission. However, the finance authority says the company is at fault.

The project completion date has been changed from last October to June next year.



« Previous Article
Next Article »

 Print    Archive    RSS

Have a question or comment about a news story? Send it to comments@wbiw.com

Advertise with 1340 AM WBIW
Find more about Weather in Bedford, IN
Advertise with 1340 AM WBIW


1340 AM WBIW, Bedford's Place To Talk. Serving Lawrence and surrounding counties since 1948!

© 2018 Ad-Venture Media, Inc. All Rights Reserved.   WBIW.com and Listen Live Powered by HPC

Advertise  |  Careers  |  Contests  |  About  |  Feedback  |  Public File