Work Progresses On Jackson County Bridges, But Slowed Because Of Delays
Updated November 24, 2015 7:31 AM
 Print    Archive    RSS

(SEYMOUR) - As work progresses on one Jackson County bridge, renovation of another bridge has run into some troubled water.

The Seymour Tribune reports, that's because of flooding in the spring and summer, the completion date for the Cavanaugh Bridge in the southwestern corner of the county has been extended. But work is moving along, says Warren Martin, county highway superintendent.

At the Shieldstown Covered Bridge in the center of the county, however, work has been stalled for about eight weeks because nearly 70 percent of the wood the contractor, Duncan Robertson Inc. of Franklin, obtained for the sides of the bridge was rejected. It was not up to national historic preservation standards.



« Previous Article
Next Article »

 Print    Archive    RSS

Have a question or comment about a news story? Send it to comments@wbiw.com

Advertise with 1340 AM WBIW
Find more about Weather in Bedford, IN
Advertise with 1340 AM WBIW


1340 AM WBIW, Bedford's Place To Talk. Serving Lawrence and surrounding counties since 1948!

© 2018 Ad-Venture Media, Inc. All Rights Reserved.   WBIW.com and Listen Live Powered by HPC

Advertise  |  Careers  |  Contests  |  About  |  Feedback