Bedford Board of Works and Safety approve bids for 2022 road resurfacing projects

BEDFORD – Bedford Street Commissioner David Flinn addressed the Bedford Board of Works and Safety about the 12 roads set to be resurfaced in 2022 and the acceptance of the bids sent in for the services.

Bedford Street Commissioner David Flinn

Two official bids were received by the board from Flynn & Sons Excavating & Paving, and Milestone Contractors sent in bids for their services to complete the project. The price of the bid for Flynn & Sons was $824,738.19, while Milestone Contractors bid was set at $996,695.35.

After taking time to review the two bids, Flinn recommended the bid be awarded to Flynn & Sons Excavating & Paving for $824,738.19, as it was the lesser of the two values and deemed most responsible for the city.

Streets to be resurfaced in 2022 include:

  • Tunnelton Road
  • 18th Street
  • 17th Street
  • 24th Street
  • J Street
  • 39th Street
  • I Street
  • H Street (16th-US Hwy 50 to 22nd Street)
  • 14th Street
  • Pumphouse Road
  • H Street (25th to I Street)
  • Leatherwood Road