(SALEM) – An informational project web page is now available for the upcoming reconstruction project in Salem. The project is currently scheduled to let to contractors in August 2021, with construction beginning in November.

The $8.7 million contract includes the following:

  • Reconstruction of State Road 56 from .09 mile east of State Road 60 to .08 mile east of State Road 135
  • Asphalt resurface on State Road 135 from State Road 56 to .72 mile north of State Road 56
  • Bridge replacement on State Road 56 over Brock Creek

Construction is expected to be complete in June of 2023. 

More information about the contract, including project plans, maintenance of traffic, cost and timeline, can be found here.